Project:
MEYERSDALE BATTERY ENERGY STORAGE SYSTEM
Location:
GARRETT, PA

JJB performed all facets of civil work: earthwork, concrete work and underground utility work—including site prep and balancing. Work included drilling piers, forming pads, excavation and backfill for underground conduit, yard and road stone. Because we handled the project from start to finish, it allowed control over the extremely condensed schedule requested by the customer. The site was very tight and restricting, requiring a great deal of coordination among our team to work efficiently.

 

 

“We have worked with JJ Barney on numerous projects; they have always provided us with a safe and quality project that meets schedule. They understand the importance of deadlines and our customers needs.”

–Randy Reints, Director of Construction, The Morse Group


Project:
MOTORCITY CASINO
Location:
DETROIT, MI

We’ve successfully completed a variety of jobs over the years, including building addition foundations, walls, floors, truck docks, decorative concrete, parking structure, valet area, sidewalks and curbs. Working inside and outside an operating casino presents its challenges, but we met those challenges head-on without impacting the customer.

 

“I’m always impressed with the level of service I find when working with JJ Barney. Their employees always respond quickly and act immediately to address any problems that arise.”

–Brian Deming, Vice President, MiG Construction


Project:
RAMSEY SUBSTATION
Location:
RAMSEY, IN

JJB performed work in a live substation from the ground up. We successfully built a flat surface on the side of a hill, completed site balancing with cuts and fills, created a drainage system and surfaced drainage improvements, drilled through solid bedrock and built slab foundations. Building on a flat site on existing bedrock, we had to navigate challenges because of the limestone bedrock on top of less-than-ideal weather conditions. Despite the challenges, we successfully completed the job and strengthened our process of anchoring in proposed foundations to the bedrock in lieu of drilling to greater depths.

 

 

“JJ Barney is an excellent company to work with. Their knowledge and expertise allowed us to finish our project ahead of schedule and under budget. I look forward to working with them on all of our future projects.”

–Bret Wheatlake, Estimating and Business Development Manager, The Hydaker-Wheatlake Co.


Project:
ITC TRANSMISSION CO. VISTEON SUBSTATION
Location:
WAYNE, MI

JJB performed earthwork and drainage work in an existing substation that was causing drainage issues to surrounding residential properties. Working under adverse conditions caused by the ponding water, we made vast improvements to create detention areas and drain those areas by gravity and force.

 

 

“JJB is an extremely reliable company that ITC has used for the past 13 years to provide a great variety of our civil construction needs; and has done so with high quality and nearly zero subcontracting.”

–Tom Kirby of ITC Transmission Co.


 

PROJECTS

 

 

PROJECT: Ambassador Bridge
LOCATION: Detroit, MI

 

JJB replaced expansion joints, performed main span pavement removal and replacement along with barrier walls. We worked 150 feet in the air under an operating bridge. Dealing with traffic, tight lanes, extreme weather conditions and logistical challenges, we completed the job on schedule with no issues.


 
 

PROJECT: ITC Transmission CO. Bunce Creek
LOCATION: Marysville, MI

 

We removed existing foundations and installed reactor foundations and containment pits in an operating substation. The result of the job was extremely positive with no errors, accidents or delays.